Denison Winery Development Wins Rezoning for 96 Acres

Denison City Council approved rezoning for a 96-acre Landon Winery project on US 75 near the Red River.

Jason Northcutt

The Texas Land Agent

6 min read50 views

Denison Winery Development Wins Rezoning for 96 Acres
Development·Grayson

Denison City Council has approved rezoning for the Denison winery development, a 96-acre project planned by Landon Winery president Bob Landon on US 75 near the Red River. KTEN reported the approval on Nov. 18. The Planning and Zoning Commission had already recommended it unanimously, according to the Herald Democrat.

The zoning is settled. Almost nothing else is. No budget or opening date has been published, the nearest sewer line is about half a mile away, and the first grapes are years out. For Grayson County landowners, the Denison winery development is a live lesson in what a rezoning delivers and what it does not.

What Is the Denison Winery Development?

It is a mixed-use destination built around a working vineyard. KXII reported that the plan includes a vineyard, a pecan orchard, a distillery, a hotel, cabins, and both single-family and multifamily housing. KTEN's earlier coverage adds a winery and restaurants, with construction in six phases.

Item Detail
Site About 95.935 acres at 6845 N. Highway 75, Denison
County Grayson
Developer Bob Landon, president of Landon Winery
Planned uses Vineyard, pecan orchard, winery, distillery, hotel, cabins, restaurants, single-family and multifamily housing
Phasing Six phases
Planning commission Unanimous recommendation to approve
City Council Approved. Vote count not published
Budget and opening date Not published

Sources: KXII, Herald Democrat, KTEN.

Landon already runs a tasting room on West Main Street in Denison, open since 2022 according to Texas Wine Lover. The Denison winery development is a different scale. KXII reported that he wants the property to feel like a European village, with everything close by.

Map of the Tract

What Did Denison City Council Approve?

One thing: a zoning change. The commission agenda cited by KXII shows the request behind the Denison winery development moved the tract from a Light Industrial district to a Planned Development overlay for mixed use.

Before After
Base zoning Light Industrial (LI) Planned Development (PD) Overlay
What governs the uses The city's light industrial district The ordinance written for this tract
Corridor rules Highway Oriented and Corridor Overlay (HO) Still inside the HO District

The site has an industrial past. The Herald Democrat reported that it is the northern portion of the former Johns Manville property, and that the project has been in the works for about two years.

Why Does a Planned Development Matter to Landowners?

A standard zoning district comes with a fixed list of uses. A winery, a hotel and housing on one tract fit none of them. A planned development is zoning written for a single property: the owner and the city agree on a concept plan, a mix of uses and site-specific standards. For the Denison winery development, that ordinance now governs the tract.

Three points carry beyond Denison.

Zoning runs with the land. The entitlement belongs to the tract, not the applicant. If the property sells, the approved uses go with it, subject to the terms of the ordinance.

The concept plan binds the owner. A PD buys flexibility at the price of commitment. A material change to the plan typically means another trip through the planning commission and the council.

Industrial zoning is not a life sentence. The commission voted unanimously and the council approved. A tract zoned for industry decades ago can be repositioned when a city sees a better fit.

What Has to Happen Before Anything Opens?

Rezoning is step one for the Denison winery development. KXII's reporting lays out the rest, and Landon called utilities the biggest challenge.

  1. Water. The existing line is six inches. "We have a water line out there, but it's a six-inch water line," Landon told KXII. He said that covers a wine room but not a hotel.
  2. Sewer. The nearest line is about half a mile away.
  3. Power. Electric lines have to go underground.
  4. Roads. They have to be built.
  5. Vines. Landon estimates at least two years from the start of dirt work before the vineyard goes in.
  6. Grapes. He expects the first crop three to five years after planting.

The coverage does not say who pays to extend the lines. That question usually decides whether a phased project holds its schedule. It is the same one shaping data center sites across Texas: the entitlement gets the headline, and the infrastructure sets the pace.

Landon is not selling a fast timeline. "It's going to take a while," he told KTEN, "but it's going to be great."

What Does the Denison Winery Development Mean for Grayson County Land?

Most of the attention on Grayson County land development has gone to Sherman's semiconductor plants and the subdivisions following them up US 75. The Denison winery development points to a third category: destination and agritourism use on highway frontage.

  • Frontage plus a natural feature is worth pricing. This tract has US 75 visibility and the Red River. Few have both.
  • Utilities are the real value driver. A six-inch water line and a sewer main half a mile off will shape the Denison winery development more than the zoning did. Check both before you price any tract.
  • Do not expect an immediate ripple. In NTREIS closed sales of 10 to 50 acre vacant tracts, Grayson County held near $30,000 per acre for three years, according to our North Texas land prices analysis. One rezoning does not move a county median.
  • Agricultural valuation takes time to earn. Texas open-space appraisal generally requires agricultural use in five of the preceding seven years. A former industrial tract planted in vines would have to build that record.

What to Watch Next

Four items will show how fast the Denison winery development moves:

  • Utility and road agreements between the developer and the city
  • The first plat and site plan, which will show what phase one includes
  • Any published budget, timeline or incentive request
  • Access design on US 75, where TxDOT has a say

The Denison winery development has its zoning. Whether it becomes the destination Landon describes depends on pipes, pavement and several growing seasons.

Own Land on the US 75 Corridor?

If you own acreage in Grayson County and want to know what your zoning allows, or what a rezoning could open up, send me the address. I'll pull the zoning, the overlay districts, the utility picture and recent comparable sales, then walk you through what I find. You can also read more about how I work with land buyers and sellers across North Texas.

References

Related: Texas Data Center Boom Is Reshaping Rural Land Markets

Related: Texas Land 1031 Exchange: When Working the Dirt Costs You

Frequently asked

Where is the Denison winery development located?
The site is about 96 acres at 6845 N. Highway 75 in Denison, Grayson County, along US 75 near the Red River crossing.
What did Denison City Council approve?
The council approved rezoning the tract from a Light Industrial district to a Planned Development overlay that allows mixed use. Plats, site plans and permits come later.
When will the Denison winery development open?
No opening date has been published. Water, sewer, power and roads come first. The developer estimates at least two years before vines are planted and three to five more before the first grapes